The map below shows the location of Hải Ninh commune, the approximate location where the plant would be built, in Hải Hậu district, Nam Định province.
{{#display_point:20.10120, 106.21355|width=600|height=500|type=hybrid|zoom=13}}
==Background==
*Phase II, Unit 1 - 600 MW - Cancelled
*Phase II, Unit 2 - 600 MW - Cancelled
==Financing==
The Investment Certificate for the power station was issued in in January 2017. The sponsors will finance the project on a 75:25 debt to equity ratio – seeking US$1.56 billion in debt. Lenders in discussion for funding the bank include the export credit agencies Export–Import Bank of Korea (Kexim) and Korea Trade Insurance Corporation (K-sure), and the banks Mizuho Financial Group (Lead Arranger), DBS, DZ Bank, Korea Development Bank, MUFG, and Standard Chartered. Financial close is expected in mid-2018.<ref>[https://www.marketforces.org.au/research/vietnam/nam-dinh-1/ "Nam Dinh 1 (1200 MW),"] Market Forces, updated Feb 20, 2018</ref>
==Project Details==