In April 2006, PNM Resources acquired the plant from Sempra.  In June 2007, PNM Resources entered a joint venture (along with Bill Gates’s Cascade Investments) with EnergyCo, passing on the power contracts of the current and future Twin Oaks units to EnergyCo.<ref>[http://uk.reuters.com/article/oilRpt/idUKN1317867620070413 PNM Texas Coal Plant to Go to Bill Gates Venture], ''Reuters UK'', April 13, 2007.</ref>
 
In April 2006, PNM Resources acquired the plant from Sempra.  In June 2007, PNM Resources entered a joint venture (along with Bill Gates’s Cascade Investments) with EnergyCo, passing on the power contracts of the current and future Twin Oaks units to EnergyCo.<ref>[http://uk.reuters.com/article/oilRpt/idUKN1317867620070413 PNM Texas Coal Plant to Go to Bill Gates Venture], ''Reuters UK'', April 13, 2007.</ref>
 +
 +
In August 2008, PNM announced that it would not pursue the Twin Oaks expansion. No reason was given for the cancellation.<ref>[http://www.reuters.com/article/email/idUSN1248362320080812 "PNM Resources drops Texas coal-plant expansion,"] Reuters, August 12, 2008.</ref>
  
 
==Project Details==
 
==Project Details==
Line 10: Line 12:
 
'''Type:''' Conventional lignite<br>
 
'''Type:''' Conventional lignite<br>
 
'''Projected in service:''' 2011<br>
 
'''Projected in service:''' 2011<br>
'''Status:''' Proposed<br>
+
'''Status:''' Cancelled<br>
  
 
==Financing==
 
==Financing==
Line 29: Line 31:
 
* [http://www.sierraclub.org/environmentallaw/coal/plantlist.asp "Stopping the Coal Rush"], Sierra Club, accessed January 2008. (This is a Sierra Club list of new coal plant proposals.)
 
* [http://www.sierraclub.org/environmentallaw/coal/plantlist.asp "Stopping the Coal Rush"], Sierra Club, accessed January 2008. (This is a Sierra Club list of new coal plant proposals.)
  
[[Category: Texas proposed coal plants]][[Category: Energy]][[Category: Active US coal plant proposals]]
+
[[Category: Texas proposed coal plants]][[Category: Energy]][[Category: Cancelled US coal plant proposals]]

Revision as of 05:31, 18 August 2008

{{#badges: CoalSwarm}} Sempra Generation, a subsidiary of Sempra Energy, proposed a 600 MW power plant as a third generating unit at its 350 MW Twin Oaks Power Plant in Bremond, TX.[1] Sempra Generation filed for an air permit with the Texas Commission on Environmental Quality in July 2005; as of Dec. 2007, the permit was still pending.[2]

In April 2006, PNM Resources acquired the plant from Sempra. In June 2007, PNM Resources entered a joint venture (along with Bill Gates’s Cascade Investments) with EnergyCo, passing on the power contracts of the current and future Twin Oaks units to EnergyCo.[3]

In August 2008, PNM announced that it would not pursue the Twin Oaks expansion. No reason was given for the cancellation.[4]

Project Details

Sponsor: EnergyCo
Location: Bremond, Robertson County, TX
Capacity: 600 MW
Type: Conventional lignite
Projected in service: 2011
Status: Cancelled